Schuylkill Valley Metro SVM   Project List   SEPTA  
Search
  History   Timeline   Alternatives   MIS/DEIS   Bibliography  
Major Investment Study / Draft Environmental Impact Statement
  3. Conceptual Engineering, Operations Analysis, and Costs
Previous Up Next

3.1.5 RIGHT-OF-WAY


As part of the construction of the SVM and in particular as a result of the construction of additional tracks as well as the construction of new stations and expansion of existing stations, properties adjacent to the proposed alignment would be impacted to varying degrees. As noted in Chapter 5, the footprint for the project encompasses requirements for all alternatives. The specific impacts and requirements for property will be determined during preliminary engineering. Table 3.1-2 [PDF] summarizes the potential property impacts that may occur based on the extent of the project footprint.

New station developments are generally located in suburban areas and/or currently vacant parcels with minimal negative impacts to adjacent property owners. The vast majority of impacts to property parcels would result in no loss of function or operation to the property, characterized by sliver takes in unused slope areas between the existing railroad right-of-way and those areas of adjacent parcels that are in use. To identify an appropriate budget for the property acquisition that will be required, an analysis was conducted for light rail and commuter rail alternatives based on classifications of the level of impact to the identified parcels and using tax assessment value data for those parcels. The assessed values may not represent actual market values and in some cases these data were not available and allowances had to be made. The overall estimated budget for property acquisition therefore, is felt to be adequate in whole, but not at the level of each parcel or within short segments of the project. This is particularly true given the fact that the exact location of passing sidings could still change during preliminary engineering resulting in a shift in impacts. Additional information on impacts to adjacent properties can be found in Section 5.3.4 of Chapter 5.

A second source of property cost for SVM right-of-way is in the form of an allowance for the entire project that covers the negotiation of an agreement with NS, any additional construction costs required to reach an agreement that are not specified in Technical Report 2.7 - Capital Cost Estimation Results, costs for access to the NS right-of-way, resolution of indemnification issues, and a capitalized value for long-term impacts on maintenance and operation. These costs are directly and indirectly related to establishing - or acquiring rights for the use of - SVM right-of-way. Also covered in this allowance are costs associated with similar issues with CSX, Amtrak, and PECO. While the breakdown of costs covered by this allowance may be different for each alternative, it is felt that the order of magnitude of the total is the same, and there are no indications that one alternative would require a significantly lower allowance than another.

SVMetro.com
Copyright © 2006 Lucius Kwok
Previous Up Next