Table 3.4-1 Soft Cost Add-On Percentages |
||||
|
Category |
Engineering |
Project Management |
Construction Management |
Total |
|
Roadway |
6% |
6% |
8% |
20% |
|
Guideway |
6% |
6% |
8% |
20% |
|
Trackwork |
6% |
6% |
8% |
20% |
|
Stations |
6% |
6% |
8% |
20% |
|
Traction Power |
6% |
6% |
8% |
20% |
|
Train Control |
6% |
6% |
8% |
20% |
|
Communications |
6% |
6% |
8% |
20% |
|
Fare Collection |
3% |
6% |
8% |
17% |
|
ROW Acquisition |
0% |
6% |
0% |
6% |
|
Utility Work |
6% |
6% |
8% |
20% |
|
Special Conditions |
6% |
6% |
8% |
20% |
|
Shops & Yards |
6% |
6% |
8% |
20% |
|
Vehicles |
3% |
6% |
0% |
9% |