Capital Cost Estimate for Route 100 Extension

The SEPTA Route 100 extension to King of Prussia and Valley Forge extends the Route 100 trolley (the Norristown High Speed Line) by 4.9 route miles. Stations on this line would include:

  • King of Prussia Station, adjacent to the park and ride lot on Bill Smith Boulevard. (Elevated station.)
  • Plaza-Court Station, at the King of Prussia mall complex, adjacent to the Strawbridges parking garage. (Elevated station.)
  • First Avenue Station, in the King of Prussia Business Park. (Elevated station.)
  • Valley Forge Station, adjacent to the Valley Forge Towers apartments. (At-grade station.)
Hard Construction Category Unit Costs (Rail) quantity unit cost/unit amount
1. Guideway (to provide foundation for track)
    At-grade - double track 2.7 miles $4,752,000 $12,830,400
Elevated structure - double track 2.2 miles $31,680,000 $69,696,000
2. Trackwork
Ballasted track, 115 lb. 5.4 miles $792,000 $4,276,800
Direct fixation track, 115 lb. 4.4 miles $1,320,000 $5,808,000
Ballasted double crossover 1 unit $280,000 $280,000
Direct-fixation double crossover 2 units $450,000 $900,000
Junction with Route 100 1 unit $280,000 $280,000
4. Systems
Electrification - third rail 9.8 miles $369,600 $3,622,080
Substations (750 V DC system) 9.8 miles $1,214,400 $11,901,120
Signalization 9.8 miles $792,000 $7,761,600
Communications 9.8 miles $211,200 $2,069,760
5. Stations
Elevated - side platforms 3 stations $8,000,000 $24,000,000
At-grade - side platforms 1 stations $4,000,000 $4,000,000
Station signage, graphics, artwork 4 stations $215,000 $860,000
Surface parking lot 2000 spaces $5,000 $10,000,000
subtotal 1-5 $158,285,760
Add-On Category Unit Costs (Rail) percent of categories amount
6. Special Conditions 11% of 1-5 $17,411,434
subtotal 1-6 $175,697,194
7. Mobilization 3% of 1-6 $5,270,916
subtotal 1-6 $180,968,109
8. Contingency 25% of 1-7 $12,667,768
subtotal 1-8 $193,635,877
9. Soft Costs
Engineering and design 11% of 1 - 7 $19,906,492
Construction management 5% of 1 - 7 $9,048,405
Project management 7% of 1 - 7 $12,667,768
Agency costs 3% of 1 - 7 $5,429,043
Insurance 5% of 1 - 7 $9,048,405
subtotal 1-9 $56,100,114
Grand total $249,735,991
All dollar values in year 2000 dollars.
Sources:
SEPTA Capital Budget FY 2006
Roosevelt Boulevard Corridor Study - Capital Costs

SVMetro.com
Copyright © 2006 Lucius Kwok